Payment & collections

Contractor Payment and Collections in California

California gives contractors three statutory remedies when payment does not arrive: the mechanics lien, the stop payment notice, and the claim against a payment bond. They reach different targets — the property, the money still held, and a surety — and a contractor is rarely choosing just one. All three share a single prerequisite, and all three run on deadlines that are unusually unforgiving. This hub, reviewed by Jayson R. Elliott, maps the framework and routes to the detailed guides.

First, the statute numbers changed

Anyone researching California construction payment law will encounter two different sets of section numbers, and one of them is no longer law.

The former Mechanics Lien Law occupied Civil Code sections 3082 through 3267. Senate Bill 189 repealed that entire framework and replaced it, operative July 1, 2012, with a new scheme at Civil Code sections 8000 through 9566. The recodification was largely a reorganization rather than a rewrite — much of the substance carried over — but every section number changed, along with some of the terminology.

Two vocabulary shifts matter for searching and for reading older material. What used to be called the “original contractor” is now the “direct contractor.” What used to be called a “stop notice” is now a “stop payment notice.”

The practical warning is straightforward: a great deal of otherwise useful material online, including law firm articles and lien service pages, still cites the 3082-series numbers. Substance in those sources is often still sound; the citations are not. Anything that turns on a specific section number should be checked against the current code.

Where the law actually lives now Civil Code §§8000–9566 — the current framework, operative July 1, 2012 (SB 189, Stats. 2010, ch. 697). Works of improvement generally: §8000 et seq. Private works: §8170 et seq. Public works: §9100 et seq. Civil Code §§3082–3267 are REPEALED. Do not rely on them.

Three remedies, three different targets

The reason California provides several remedies is that each reaches a different asset, and which ones are available depends on the project.

A mechanics lien attaches to the improved property itself. It is the remedy most contractors think of first, and it is generally unavailable on public works — a public agency’s property is not subject to it, which is why the public works track exists separately.

A stop payment notice reaches funds still held by the owner or, on some projects, the construction lender. Its practical virtue is that it targets money that has not yet moved rather than requiring foreclosure on real property. Its practical limit is that it only works while there are funds left to stop.

A payment bond claim reaches a surety rather than the owner or the property. On public works this is often the primary remedy precisely because liens are unavailable. Note the distinction from the license bond: a contractor’s license bond under Business and Professions Code section 7071.6 is a different instrument with a different purpose, and it is not a payment bond.

The prerequisite: preliminary notice

This is the single most important operational point on the page, because one document protects all three remedies and missing it forfeits them together.

Civil Code section 8200 provides that before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond, a claimant shall give preliminary notice to the owner or reputed owner, the direct contractor or reputed direct contractor to which the claimant provides work, and the construction lender or reputed construction lender if there is one. Section 8200 further provides that compliance is a necessary prerequisite to the validity of a lien claim or stop payment notice.

The deadline is short. Preliminary notice must be given not later than 20 days after the claimant first furnishes work on the work of improvement. A notice served late is not necessarily worthless — the statute limits the claim to work furnished within a defined lookback period rather than voiding rights outright — but the safe practice is to treat the 20 days as absolute and serve at the start of every job as a matter of routine, not as a response to a payment problem that has already developed.

The dedicated guide covers who must serve notice, who is excepted, and what the notice has to contain.

The mechanics lien, in outline

Two deadlines govern a mechanics lien, and they are sequential.

The first is the deadline to record the claim of lien, set by Civil Code sections 8412 and 8414 — section 8412 for direct contractors, section 8414 for other claimants. Absent a recorded notice of completion or notice of cessation, the window is generally 90 days after completion. Recording a notice of completion or cessation shortens it, and the shortened periods differ between direct contractors and other claimants. Because published sources conflict on those specific shortened figures, this page does not state them; the lien guide will, once the sections have been read against the current code.

The second is the deadline to enforce. Under Civil Code section 8460, an action to foreclose the lien must be commenced within 90 days after recording the claim of lien. Miss it and the lien expires and becomes unenforceable — recording is not the end of the process, it starts a new clock.

These deadlines are strict, and a contractor negotiating in good faith with an owner who keeps promising payment can talk their way past a deadline that will not be reopened. The correct instinct is to preserve the remedy first and negotiate from there.

Licensure comes first

None of these remedies helps a contractor who cannot bring an action at all. Business and Professions Code section 7031 bars any person acting in the capacity of a contractor from bringing or maintaining an action to collect compensation for work requiring a license without alleging licensure at all times during performance — regardless of the merits — and separately allows the customer to recover all compensation already paid.

A payment dispute is therefore the wrong moment to discover a licensure gap, and the licensing pillar covers what that costs.

Guides in this section

Guide

What it covers

Primary authority

Filing a Mechanics Lien

Recording deadlines, contents, service, and enforcement

Civ. Code §§8400–8494

Preliminary Notice

Who must serve, on whom, by when, and what it protects

Civ. Code §§8200–8216

Stop Payment Notices

Reaching undisbursed funds, on private and public works

Civ. Code §§8500 et seq.; §§9350 et seq.

Payment Bond Claims

The surety remedy where a lien is unavailable

Civ. Code §§8600 et seq.; §§9550 et seq.

Public Works Payment

Prevailing wage and payment on public projects

Pub. Contract Code §§10100–10870; Lab. Code §§1720–1743

Subcontractor Payment Rights

Remedies when the general contractor doesn’t pay

Civ. Code §§8000–9566

Before you ask

Questions contractors ask first.

What are a California contractor's options when a customer will not pay?

California provides three statutory remedies under Civil Code sections 8000 through 9566: a mechanics lien against the improved property, a stop payment notice reaching funds still held by the owner or construction lender, and a claim against a payment bond. Which are available depends on the project — mechanics liens are generally unavailable on public works, which is why bond claims dominate there.

Are California mechanics liens still under Civil Code §3082?

No. Civil Code sections 3082 through 3267 were repealed effective July 1, 2012 by Senate Bill 189 and replaced with Civil Code sections 8000 through 9566. The substance largely carried over, but every section number changed, and a great deal of material still online cites the repealed numbering.

How long do I have to serve a California preliminary notice?

Preliminary notice must be given not later than 20 days after the claimant first furnishes work on the work of improvement. Under Civil Code section 8200, that notice goes to the owner or reputed owner, the direct contractor, and the construction lender if there is one — and compliance is a necessary prerequisite to the validity of a lien claim or stop payment notice.

Does one preliminary notice protect all three remedies?

Yes. Civil Code section 8200 frames preliminary notice as the step required before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond. That is why the 20-day deadline matters so much: a single missed notice can forfeit all three remedies at once.

How long do I have to enforce a recorded mechanics lien in California?

Civil Code section 8460 requires an action to enforce the lien to be commenced within 90 days after recording the claim of lien. If suit is not filed in that window the lien expires and becomes unenforceable — recording the lien starts a new deadline rather than completing the process.

Is a contractor license bond the same as a payment bond?

No. The license bond required by Business and Professions Code section 7071.6 is a condition of holding a license and is capped at $25,000, with aggregate liability on most claims limited to $7,500. A payment bond on a construction project is a separate instrument under Civil Code sections 8600 and following for private works and sections 9550 and following for public works.

Talk to an Attorney Today

If this describes your situation, an attorney affiliated with Bay Legal PC, CA Bar No. 332479, can review it with you.